S-3.3, r. 3 - Regulation respecting the safety of the Réseau électrique métropolitain

Full text
14. The operator develops and applies appropriate procedures for daily operational tests before the daily operation of the rolling stock used for the movement of users.
The procedures developed must specify the procedures that apply to every rolling stock item when defects have been detected on it.
O.C. 161-2018, s. 14.
In force: 2018-03-22
14. The operator develops and applies appropriate procedures for daily operational tests before the daily operation of the rolling stock used for the movement of users.
The procedures developed must specify the procedures that apply to every rolling stock item when defects have been detected on it.
O.C. 161-2018, s. 14.